Page 1 Page 1 Фігура_2_копія Фігура_3_копія Фігура_4_копія Page 1 Copy 3 PBS-logo-footer Group 28 Created with Sketch. Page 1 Page 1 Fill 1 Fill 1 Page 1 Page 1 Page 1 Combined Shape Fill 1 Fill 1 Page 1 Group Page 1 Fill 1 Rectangle 14 Rectangle 14 Copy Page 1 Page 1 Page 1 icons complete-icon location Page 1 Page 1 Copy 4 1StatusIcon 1StatusIcon 1StatusIcon Combined Shape Created with Sketch.

July 30, 2018

Н-03 road: repairs are in full swing

We're now working in Bukovyna region. On the road H-03, Zhytomyr - Chernivtsi, near the village of Dynivtsi in Novoselytsky district, the road base has been strengthened with cold recycling.

80% of the plot has been complete. We now continue with the leveling asphalt concrete layer, applying gravel-sand composition. "PBS" brigades are now at 341st kilometer. The total area to be repaired is 337 km + 568 km 342 + 700 km.