The repairs are now less chaotic, compared to last week. The drainage system has been improved.
During the weekend, PBS workers have fixed the profile of the road.Today in the morning they began spreading the gravel-sand composition over the base. Those are initial steps in order to prepare the road for cold recycling regeneration.
As soon as regeneration finishes, asphalt-concrete coating will be applied.