Page 1 Page 1 Фігура_2_копія Фігура_3_копія Фігура_4_копія Page 1 Copy 3 PBS-logo-footer Group 28 Created with Sketch. Page 1 Page 1 Fill 1 Fill 1 Page 1 Page 1 Page 1 Combined Shape Fill 1 Fill 1 Page 1 Group Page 1 Fill 1 Rectangle 14 Rectangle 14 Copy Page 1 Page 1 Page 1 icons complete-icon location Page 1 Page 1 Copy 4 1StatusIcon 1StatusIcon 1StatusIcon Combined Shape Created with Sketch.

Oct. 9, 2018

Yabluniv - Deliatyn road: PBS asphalt supply trucks are on the way

PBS workers are ready for night asphalting. The first trucks loaded with coarse asphalt mixture went to Bereziv. There is already a brigade waiting for it to asphalt almost a kilometer section of the road.

"Yesterday we made almost a kilometer length of leveling layer of CA . Today and tomorrow we're planning to do the same. We're work very quickly, no local company can boast such a rate. Same thing last year", - Mykola Serhiychuk, chief engineer of PBS .

In the afternoon, the brigade entitled to strengthening the base, has installed nearly 700 tons of crushed stone mixture. A large amount of work indeed. Same thing for the previous days.

"Weather conditions allow us to work fast. Claims by local residents for some delays are unreasonable, as we work at the exactly same rate on our other projects", - PBS road builders.

 18 kilometers of the road have been already repaired.