The bridge over the Styr river in Lutsk is halfway completed. The repair works in Lutsk are steadily proceeding. Right now PBS road builders are working on the second traffic lane of the bridge.
"One part of the bridge has already been asphalted. The repaired deformation seams have been covered with leveling coarse-grained asphalt concrete layer. The lane is now open for traffic. Another one is closed for repairs", - Ruslan Zinko, PBS foreman.
PBS workers are now dismantling the old concrete to smooth-out deformation seams. As always, waterproofing and asphaling will be the next step.
"The works will be the same as on the first traffic lane, nothing more to say here. We're trying to cause minimum inconveniences for drivers, we apologize for temporary discomfort", - Ruslan Zinko.