PBS roadmasters are again returning to Dolyna. Machinery has been deployed, the repairs shall start tomorrow of the unfinished section, which is located on the 41 km of the road H-10, Stryi - Mamalyha.
"Some of our machinery is still arriving. It will appear in Dolyna during the day. We hope that from the third attempt we will be able to complete the repairs", - Volodymyr Bygar, foreman of PBS.
The delay in repairs of the road occurred due to insufficient funding of the project. On a 300-meter section, cold milling of the old road surface has already been carried out and a layer of gravel-sand composition mix has been applied to strengthen the road base. The only thing left to do cold recycling regeneration and put asphalt afterwards.
"Due to the fact that road repair failed to complete during the previous campaign, we've suffered financial losses. The usage of the unfinished road construct caused losses of dry material, thus we'll have to add in additional resourses. We will conclude the gravel-sand composition again and immediately strengthen it by adding mineral binders. As soon as those preparatory works are complete, we will proceed to asphalting", - PBS road builders.
The Ivano-Frankivsk region Road Service informs that, together with Ukravtodor officials, an appeal to the Government has been sent to the Government concerning the Decree No. 817 issued October 10, 2018, on funds redistribution for repair works on the roads H-10, Stryi-Mamalyga (near the town of Dolyna) and P-62, Kryvorivnia - Chernivtsi (in the village of Velykyi Rozhyn, Kosiv district). The corrections are now being made to Financial Plan in the Ministry.
With the assistance of Oleksandr Shevchenko, agreements were reached in order to continue the works immediately.