Repair work on the road P-21 does not stop. "PBS" employees are regenerating the road in the village of Verkhnii Bystryi, Mizhhirya district. Old pavement pulverizing and installation of additional material to strengthen the base is carried out near the village of Torun. Of course, continuous heavy rains affected the pace of the project. However, the work is being carried out according to the schedule. The section being repaired is 14 kilometers long.
The following works are underway in separate sections:
- Torun village ➡️ pulverizing;
- Torun village ➡️ additional gravel-sand material, cold recycling regeneration;
- Verkhnii Bystryi village ➡️ lower layer of asphalt concrete.
5 kilometers of the highway have been asphalted. Along the entire length of the road we are restoring retaining walls, eliminating landslides and strengthening bridges.
The works are carried out 24h.