Page 1 Page 1 Фігура_2_копія Фігура_3_копія Фігура_4_копія Page 1 Copy 3 PBS-logo-footer Group 28 Created with Sketch. Page 1 Page 1 Fill 1 Fill 1 Page 1 Page 1 Page 1 Combined Shape Fill 1 Fill 1 Page 1 Group Page 1 Fill 1 Rectangle 14 Rectangle 14 Copy Page 1 Page 1 Page 1 icons complete-icon location Page 1 Page 1 Copy 4 1StatusIcon 1StatusIcon 1StatusIcon Combined Shape Created with Sketch.

Aug. 2, 2020

Sivka Voinylivska bridge: carriageway asphalting completed

At km 9+442 of the motorway T-09-10 Burshtyn - Kalush, "PBS" is performing bridge construction works across the Dniester river near Sivka Voynylivska, Kalush district. Currently, contractor company employees are busy installing the fencing rails. Bridge entry sections are currently being installed. Asphalt concrete is being arranged on the carriageway.

Bridge construction was resumed back in 2019, particularly the bridge girder structure was fully mounted; reinforced concrete overlay plate mounting was initiated.

In 2020, the following works are underway:

- reinforced concrete overlay plate mounting;
- waterproofing;
- asphalt concrete paving - carriageway and entry sections;
- barrier fencing installation;
- illumination, road markings;
- road sign installation.

The Sivka Voinylivska bridge is an important infrastructure facility, scheduled to be commissioned by the end of the year.