Repair of the road P-21 Dolyna - Khust is underway. We have already reached the border of Mizhhiria.
Road base regeneration in the villages of Maidan and Soimy has been completed.
The junction with the road T-07-17 Nyzhni Vorota - Volovets - Mizhhirya has been arranged. We are now busy arranging the edge trays.
The next step is to restore the subsoil, which was swept away by the flood. We are also doing calculations in order to constuct the embankment slopes. Due to heavy rain, we cannot proceed with coarse-grained asphalt concrete installation. As soon as weather conditions allow, we will start at once.