Road surface loosening commencing on the road P-21 Dolyna - Khust in the Zakarpattia region, at km 128+770. We started from the end of the section and are moving towards the village of Iza.
The road base will be later reinforced using the cold recycling technology, two layers of asphalt concrete will be pressed - 10 cm coarse-grained and 5 cm crushed stone-mastic.
At the same time, concomitant works are underway in the forn of ditch deepening, river bank strengthening, barrier fence installation and drainage tray adjustment.
According to the project, "PBS" will repair the road P-21 Dolyna-Khust in full amount. Last year, almost 45 kilometers of the road within the Transcarpathian region were rebuilt, starting from the Torun mountain pass, up to the village of Vuchkove. In 2021, the operations will continue through villages Nyzhnii Bystryi, Berezovo, Horinchovo and Iza.
As for the P-21 in general, this year it is planned to initiate similar repair activity within the Ivano-Frankivsk region.