The "PBS" company is working to finalize the scheduled repairs of the road T-14-19 Mykolaiv - Zhydachiv - Kalush. Our employees are now arranging the final SMA layer on the Hlibov street in Kalush. In addition, an upper asphalt concrete layer has been laid on Mostyska street. Here, too, our team has loosened the road surface, regenerated the base using the cold recycling technology and pressed a leveling layer of asphalt concrete. Sidewalks will be built on these streets and a modern roundabout ring will be constructed.
In addition to Hlibov and Mostyska streets, "PBS" has scheduled to partially repair the Yuriy Lytvyn and Okruzhna streets in Kalush. As a part of the presidential initiative "Big Construction", future plans include repairing yet another 8 kilometers of T-14-19 at km 67+776 - km 71+626 and km 72+186 - km 76+476.