Page 1 Page 1 Фігура_2_копія Фігура_3_копія Фігура_4_копія Page 1 Copy 3 PBS-logo-footer Group 28 Created with Sketch. Page 1 Page 1 Fill 1 Fill 1 Page 1 Page 1 Page 1 Combined Shape Fill 1 Fill 1 Page 1 Group Page 1 Fill 1 Rectangle 14 Rectangle 14 Copy Page 1 Page 1 Page 1 icons complete-icon location Page 1 Page 1 Copy 4 1StatusIcon 1StatusIcon 1StatusIcon Combined Shape Created with Sketch.

Nov. 9, 2021

Lytvyn street in Kalush being repaired

"PBS" is steadily approaching completion of the project T-14-19 Zhydachiv – Kalush.

Works are currently underway on the Kalush bypass road:

- road base strengthening, gravel-sand mixture installation, cold recycling regeneration (Lytvyn street);

- leveling asphalt concrete layer paving (Okruzhna street);

- for the most part, the street already has two asphalt layers on Obiizna street, which indicates the fast and high-quality output from the "PBS" team.

We will remind that the Kalush bypass with the specified streets recently became a part of the highway Zhydachiv – Kalush. However the road was so badly damaged that few cars drove on it. Now the situation has changed drstically! A few more working days and we will invite you to test the updated road.

The highway is being repaired under the presidential program "The Big Construction".