KOLOMYIA, IVAN FRANKO STREET
Repair works type
Overhaul
Segment length, km
1.0
Status
Completed as of 01.04.2018 100%
Financing source
Kolomyia town council
Client
Kolomyia City Council Communal Property Management Department
100%
Completed before 01.04.2018
1.0 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
T-26-01
CHERNIVTSI - VASHKIVTSI - PUTYLA - "RUSKA" CHKPNT (SEPARATE AREAS)
Repair works type
Current average repairs
Segment length, km
4.5
Status
Completed as of 01.04.2018 100%
Financing source
State budget, EU grant
Client
Chernivtsi region road service
100%
Completed before 01.04.2018
4.5 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
T-09-09
KOSIV - STARI KUTY
Repair works type
Current average repairs
Segment length, km
9.17
Status
Completed as of 01.12.2020 100%
Financing source
State budget
Client
Ivano-Frankivsk region road service
100%
Completed before 01.12.2020
9.17 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
T-09-02
ROZHNYATIV, SICHOVYKH STRILTSIV STREET
Repair works type
Overhaul
Segment length, km
1.3
Status
Completed as of 01.04.2018 80%
Financing source
State budget
Client
Ivano-Frankivsk region administration office
80%
Completed before 01.04.2018
1.3 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
T-09-06
IVANO-FRANKIVSK – NADVIRNA
Repair works type
Current average repairs
Segment length, km
26.7
Status
Completed as of 01.08.2020 100%
Financing source
State budget
Client
Ivano-Frankivsk region road service
100%
Completed before 01.08.2020
26.7 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
T-09-05
DELIATYN - RAKIVCHYK
Repair works type
Current average repairs
Segment length, km
28.027
Status
Completed as of 15.09.2018 55%
Financing source
State budget
Client
Ivano-Frankivsk region road service
55%
Completed before 15.09.2018
28.027 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
O-14-12-03
LVIV - SUKHORITCHIA
Repair works type
Current average repairs
Segment length, km
4.78
Status
Completed as of 01.12.2015 100%
Financing source
State budget
Client
Lviv region road service
100%
Completed before 01.12.2015
4.78 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
IVANO-FRANKIVSK, POLYOVA STREET
Repair works type
Overhaul
Segment length, km
0.729
Status
Completed as of 01.04.2018 100%
Financing source
State budget subventions
Client
Ivano-Frankivsk region administration office
100%
Completed before 01.04.2018
0.729 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
O-14-12-35
OSTRIV - CHYZHYKIV
Repair works type
Construction
Segment length, km
1.98
Status
Completed as of 01.12.2016 100%
Financing source
State budget
Client
Lviv region road service
100%
Completed before 01.12.2016
1.98 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs