O-09-08-02
YABLUNIV - DELYATYN
Repair works type
Current average repairs
Segment length, km
32.32
Status
Completed as of 02.08.2020 90%
Financing source
State budget
Client
Ivano-Frankivsk region road service
90%
Completed before 02.08.2020
32.32 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
C-14-12-32
ZHURAVNYKY - TARASIVKA
Repair works type
Current average repairs
Segment length, km
3.65
Status
Completed as of 01.06.2018 100%
Financing source
State budget
Client
Lviv region road service
100%
Completed before 01.06.2018
3.65 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
C-09-16-05
POLYANYTSIA
Repair works type
Current average repairs
Segment length, km
7.224
Status
Completed as of 01.04.2018 100%
Financing source
State budget
Client
Ivano-Frankivsk region road service
100%
Completed before 01.04.2018
7.224 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
C-09-06-08
NOVYTSIA - SEREDNIY UHRYNIV
Repair works type
Current average repairs
Segment length, km
8.28
Status
Completed as of 01.09.2018 100%
Financing source
State budget
Client
Ivano-Frankivsk region road service
100%
Completed before 01.09.2018
8.28 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
YAREMCHE, PETRASHA STREET
Repair works type
Overhaul
Segment length, km
0.35
Status
Completed as of 01.04.2018 100%
Financing source
Town's budget, regional budget
Client
Yaremche municipal service
100%
Completed before 01.04.2018
0.35 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
P-62
KRYVORIVNIA - TYUDIV
Repair works type
Current average repairs
Segment length, km
13.8
Status
Completed as of 31.12.2020 100%
Financing source
State budget
Client
Ivano-Frankivsk region road service
100%
Completed before 31.12.2020
13.8 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
ZUBRA, IVAN FRANKO STREET
Repair works type
Overhaul
Segment length, km
0.266
Status
Completed as of 31.12.2015 100%
Financing source
Zubra village council
Client
Zubra village council
100%
Completed before 31.12.2015
0.266 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
P-21
DOLYNA - KHUST
Repair works type
Current average repairs
Segment length, km
44.923
Status
Completed as of 31.12.2021 100%
Financing source
State budget
Client
Ivano-Frankivsk region road service
100%
Completed before 31.12.2021
44.923 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
ZUBRA, SKRYPNYK STREET
Repair works type
Overhaul
Segment length, km
0.23
Status
Completed as of 31.12.2015 100%
Financing source
Zubra village council
Client
Zubra village council
100%
Completed before 31.12.2015
0.23 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs