LUTSK. DUBNIVSKA.KARPENKO KARYI INTERSECTION
Repair works type
Overhaul
Segment length, km
1.0
Status
Completed as of 31.12.2018 100%
Financing source
Lutsk city council
Client
Lutsk city council's muninipal department
100%
Completed before 31.12.2018
1.0 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
LUTSK. STYR RIVER BRIDGE
Repair works type
Overhaul
Segment length, km
0.1
Status
Completed as of 01.12.2018 100%
Financing source
Lutsk city council
Client
Lutsk city council's muninipal department
100%
Completed before 01.12.2018
0.1 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
C-07-10-11
KERETSKY - BEREZNYKY
Repair works type
Current average repairs
Segment length, km
5.8
Status
Completed as of 30.09.2018 100%
Financing source
Transcarpathian RSA
Client
Transcarpathian RSA
100%
Completed before 30.09.2018
5.8 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
O-07-10-01
SVALIAVA - MUKACHEVO
Repair works type
Overhaul
Segment length, km
8.2
Status
Completed as of 31.08.2018 100%
Financing source
Transcarpathian RSA
Client
Transcarpathian RSA
100%
Completed before 31.08.2018
8.2 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
H-09
IVANO-FRANKIVSK, HALYTSKA STREET
Repair works type
Current average repairs
Segment length, km
0.5
Status
Completed as of 24.08.2018 100%
Financing source
Town's budget
Client
Department of communal services, transport and communications of Ivano-Frankivsk city council
100%
Completed before 24.08.2018
0.5 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
TLUMACH, HRUSHEVSKYI ST.
Repair works type
Current average repairs
Segment length, km
0.8
Status
Completed as of 31.12.2018 100%
Financing source
Tlumach municipal funds
Client
Tlumach municipal funds
100%
Completed before 31.12.2018
0.8 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
O-07-09-03
YASINIA - CHORNA TYSA
Repair works type
Overhaul
Segment length, km
7.6
Status
Completed as of 26.09.2018 100%
Financing source
Transcarpathian RSA
Client
Transcarpathian RSA
100%
Completed before 26.09.2018
7.6 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
O-07-01-07
BEREHOVO - ZATYSHNE - KIDIOSH
Repair works type
Overhaul
Segment length, km
8.1
Status
Completed as of 05.09.2018 100%
Financing source
Transcarpathian RSA
Client
Transcarpathian RSA
100%
Completed before 05.09.2018
8.1 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
O-07-01-02
BEREHOVO - BADALOVO - VARY - BORZHAVA
Repair works type
Overhaul
Segment length, km
23.97
Status
Completed as of 31.08.2018 100%
Financing source
Transcarpathian RSA
Client
Transcarpathian RSA
100%
Completed before 31.08.2018
23.97 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs