T-07-20
MIZHGIRYA - SYNEVYR
Repair works type
Current average repairs
Segment length, km
15.0
Status
Completed as of 31.12.2021 95%
Financing source
State Budget
Client
Служба автомобільних доріг у Закарпатській області
95%
Completed before 31.12.2021
15.0 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
H-10
BODNARIV BRIDGE
Repair works type
Construction
Segment length, km
0.5
Status
Completed as of 31.12.2020 100%
Financing source
State budget
Client
Ivano-Frankivsk region Road Service Department
100%
Completed before 31.12.2020
0.5 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
T-26-06
NOVOSELYTSIA BRIDGE - MARSHYNTSI - HERTSA
Repair works type
Construction
Segment length, km
323.0
Status
Completed as of 05.08.2020 100%
Financing source
State budget
Client
Chernivtsi region Road Service Department
100%
Completed before 05.08.2020
323.0 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
T-09-10
BURSHTYN BRIDGE - KALUSH
Repair works type
Construction
Segment length, km
0.24
Status
Completed as of 31.08.2020 100%
Financing source
State budget
Client
Ivano-Frankivsk region Road Service Department
100%
Completed before 31.08.2020
0.24 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
C-09-15-05
HERYNIA - BOLEKHIV
Repair works type
Overhaul
Segment length, km
4.2
Status
Completed as of 31.12.2020 100%
Financing source
Regional budget
Client
Ivano-Frankivsk Region State Administration
100%
Completed before 31.12.2020
4.2 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
YAREMCHE. STEPAN BANDERA STREET
Repair works type
Overhaul
Segment length, km
1.2
Status
Completed as of 28.12.2019 100%
Financing source
Yaremche town council
Client
Yaremche town council
100%
Completed before 28.12.2019
1.2 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
M-19
"PORUBNE" CHECKPOINT
Repair works type
Overhaul
Segment length, km
5.1
Status
Completed as of 31.10.2020 100%
Financing source
State budget
Client
Chernivtsi region Road Service Department
100%
Completed before 31.10.2020
5.1 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
P-20
SNIATYN - TIAZIV
Repair works type
Current average repairs
Segment length, km
4.0
Status
Completed as of 31.12.2020 0%
Financing source
State Budget
Client
Ivano-Frankivsk region Road Service Department
0%
Completed before 31.12.2020
4.0 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
P-21
TORUN MOUNTAIN PASS - KHUST
Repair works type
Current average repairs
Segment length, km
83.0
Status
Completed as of 31.12.2021 100%
Financing source
Transcarpathian Road Service dept.
Client
Transcarpathian Road Service dept.
100%
Completed before 31.12.2021
83.0 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs