Repair works type
Current average repairs
Segment length, km
2.0
Status
Completed as of 09.02.2022 0%
Financing source
3
Client
3
0%
Completed before 09.02.2022
2.0 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
O-03-14-82
КРИМНЕ - ЗАЛЮТТЯ - ПОЛІСЬКЕ
Repair works type
Overhaul
Segment length, km
15.0
Status
Completed as of 31.01.2022 100%
Financing source
State Budget
Client
Волинська ОДА
100%
Completed before 31.01.2022
15.0 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
T-03-02
ПІЩА - ШАЦЬК - ЛЮБОМЛЬ - КОЗИН
Repair works type
Current average repairs
Segment length, km
26.0
Status
Completed as of 31.12.2021 100%
Financing source
State Budget
Client
Служба автомобільних доріг у Волинській області
100%
Completed before 31.12.2021
26.0 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
M-19
ДОМАНОВЕ - КОВЕЛЬ - ЧЕРНІВЦІ - ТЕРЕБЛЕЧЕ
Repair works type
Current average repairs
Segment length, km
30.0
Status
Completed as of 31.12.2021 100%
Financing source
State Budget
Client
Служба автомобільних доріг у Волинській області
100%
Completed before 31.12.2021
30.0 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
NADRICHNA ST. IVANO-FRANKIVSK
Repair works type
Overhaul
Segment length, km
0.772
Status
Completed as of 31.01.2022 90%
Financing source
State Budget
Client
Івано-Франківська міська рада
90%
Completed before 31.01.2022
0.772 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
M-30
STRYI - ZNAMYANKA
Repair works type
Overhaul
Segment length, km
33.0
Status
Completed as of 31.12.2021 95%
Financing source
State Budget
Client
Служба автомобільних доріг в Івано-Франківській області
95%
Completed before 31.12.2021
33.0 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
P-38
BOGORODCHANY - GUTA
Repair works type
Current average repairs
Segment length, km
36.0
Status
Completed as of 31.12.2021 95%
Financing source
State Budget
Client
Служба автомобільних доріг в Івано-Франківській області
95%
Completed before 31.12.2021
36.0 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
T-07-20
MIZHGIRYA - SYNEVYR
Repair works type
Current average repairs
Segment length, km
15.0
Status
Completed as of 31.12.2021 95%
Financing source
State Budget
Client
Служба автомобільних доріг у Закарпатській області
95%
Completed before 31.12.2021
15.0 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs
H-10
BODNARIV BRIDGE
Repair works type
Construction
Segment length, km
0.5
Status
Completed as of 31.12.2020 100%
Financing source
State budget
Client
Ivano-Frankivsk region Road Service Department
100%
Completed before 31.12.2020
0.5 Km
Segment length
Legend
Segment length
Upper layer of asphalt concrete
Bottom layer of asphalt concrete
Scheduled repairs